Work on intersection of Sequim-Dungeness Way and Woodcock Road

November 15, 2021
 
After the bracing rains of the past week and today’s refreshing windstorm, it is supposed to be boring and sunny tomorrow.
 
But next week we will have pavement pulverizing and grinding as the existing asphalt at the Sequim-Dungeness and Woodcock Road intersection is removed. The work is scheduled for Monday, November 22 through Wednesday, November 24, with changes possible depending on the weather. You can read about it here:
 
 
Alternative routes into Sequim include heading south on Blakely Blvd. through upper Sunland and then out Taylor Blvd., or heading east on Woodcock, south on Holland, and then saying “Hi!” to the elk on Port Williams Road before proceeding into town.
 
As the Clallam County site notes, the work is expected to be completed by April, 2022. Meanwhile, you can brush up on roundabouts: